J. v. G. to Build Solar Fac­tory in Brazil

Veröffentlicht auf 18.01.2016
J. v. G. 
It's already underway. In fact, four containers have been loaded with cargo to deliver the first J. v. G. solar plant to Brazil.

Experts from the Bavarian solar manufacturer are currently packing all of the machines so that they can be shipped by sea in the next few days. They will travel to Recife, where the machines will be loaded onto trucks in the customs area for shipping across another 150 kilometers of land.

At the end of January 2016, the machines should arrive at the factory. Hans Thoma, the General Manager of J. v. G. Thoma GmbH says, "We have scheduled four weeks for construction, after which production should start."


ENF Profile von in diesem Artikel genannten Unternehmen

J. v. G. (Produktionsequipment): https://de.enfsolar.com/j-v-g
J. v. G. (Solarteure): https://de.enfsolar.com/j-v-g
Veröffentlichtung der PV Industrienachrichten ist kostenlos. Bitte senden Sie Ihre Nachrichten an