Kyocera TCL Solar Begins Construction on 13.7MW Floating Solar Power Plant

Veröffentlicht auf 22.01.2016
Kyocera 
In a joint venture, Kyocera Corporation and Century Tokyo Leasing Corporation announced today that Kyocera TCL Solar LLC has started construction of 13.7MW floating solar power plant on the Yamakura Dam reservoir, managed by the Public Enterprises Agency of Chiba Prefecture in Japan for industrial water services.

Scheduled for launch in FY2018 (fiscal year ending March 31, 2018), the plant will be comprised of approximately 51,000 Kyocera modules installed over a fresh water surface area of 180,000m2. The project will generate an estimated 16,170MWh per year — enough electricity to power approximately 4,970 typical households — while offsetting about 8,170 tons of CO2 emissions annually. This is equal to 19,000 barrels of oil consumed.

The project was initiated in October 2014, when the Public Enterprises Agency of Chiba Prefecture publicly sought companies to construct and operate a floating solar power plant to help reduce environmental impact.


ENF Profile von in diesem Artikel genannten Unternehmen

Kyocera (Solarwerkstoffe): https://de.enfsolar.com/kyocera
Kyocera (Solarmodule): https://de.enfsolar.com/kyocera
Kyocera (Komponenten): https://de.enfsolar.com/kyocera
Kyocera (Solarteure): https://de.enfsolar.com/kyocera
Veröffentlichtung der PV Industrienachrichten ist kostenlos. Bitte senden Sie Ihre Nachrichten an